Nippon Dynawave faces $10 million in penalties and a criminal referral over the Longview tank rupture that killed 11
Washington regulators say Nippon Dynawave Packaging Co. ran a white liquor tank at its Longview paper mill for 43 weeks after reports showed its walls were too thin, and fined it $9.18 million, the largest workplace safety penalty in state history.
The Washington State Department of Labor & Industries cited the company for 75 violations after a six-month investigation of the May 26 failure of the tank, known as G-tank. It released about 900,000 gallons of caustic white liquor, killed 11 workers and injured 12. The safety fine of $9,177,127 is more than three times the previous state record, $2.9 million after the 2010 Tesoro refinery explosion. The Department of Ecology added $961,000 in penalties and emergency response costs, for a total of $10,138,127. L&I said it will refer the case to prosecutors to consider criminal charges.
According to L&I, Nippon received three reports between August 2025 and February 2026 showing the tank shell had corroded below its minimum safe thickness. The agency pointed to API 653, the industry standard for tank inspection and repair, which Nippon wrote into its own procedures. Under it, a tank that falls below minimum thickness has to be repaired, run at a lower fill level or retired. Internal emails show managers discussed those options and then did nothing, the agency said. It issued 43 egregious willful serious citations, one for each week the tank stayed in service.
Investigators also found that 14 tanks on the site, G-tank among them, either missed regular internal inspections or had problems from external inspections left unfixed. Three tanks with known defects never got a fitness-for-service evaluation. For several hours after the rupture there was no employer-led incident command, and L&I said that gap contributed to four of the injuries.
Nippon said the state's description of its conduct as egregious and willful leaves out facts and context and that it will appeal, the Associated Press reported. It has 15 days to file. The company plans to restart the mill in December, and families of workers who died have filed wrongful-death suits.
Why it matters: A thickness report protects no one until someone acts on it. Anyone who inspects, repairs or shuts down plant tanks should make sure every below-minimum reading ends in a written repair, derate or retirement decision with a date.
Sources
- Nippon Dynawave faces $10 million in state penalties, costs related to deadly tank failureWashington State Department of Labor & Industries, Nov 20
- Officials: Washington pulp mill violated safety standards before ruptured chemical tank killed 11The Associated Press (Peterborough Examiner), Nov 20