Loudermilk Homes faces arbitration over water and mold in a $4 million Sandy Springs house
The owners of a Sandy Springs, Georgia, house built by Loudermilk Homes, LLC less than five years ago have moved out over water damage, mold and rotting wood, WSB-TV reported. They blame the stucco and siding work. The builder says the water came through the roof.
Johnny and Tracy Miguel told WSB-TV the trouble showed up as peeling wallpaper and ended with the family living in an Airbnb. A second-floor bedroom has been stripped to the studs, and added beams now hold up parts of a multi-story deck where wood decayed, the station reported. The house is worth more than $4 million.
Both sides agree water got in. Lauren Wayne, a structural engineer the owners hired, blames how the stucco, siding and water-resistive barriers were put on across the exterior walls, and a siding manufacturer's representative also recorded installation problems, according to documents WSB-TV reviewed. Sherwin Loudermilk, the company's founder and president, says punctures in the flat TPO roof let the water in. He cites a building-envelope specialist who inspected in February; his own written account says that specialist also thought water could have entered through a wall.
At the builder's suggestion, the owners filed a homeowners insurance claim. It was denied. The insurer's adjuster inspected on Feb. 19 and pointed to the joint where stucco meets wood siding, according to an April 7 notice the owners sent under Georgia's Right to Repair Act. Loudermilk says he offered to pay if the investigation found faulty construction and that roof damage would be the owners' cost.
The two sides never held a joint inspection, and each blames the other. The owners' lawyer invited the builder to destructive testing on July 27 and wrote the next day that no one from Loudermilk Homes came. Loudermilk says so much had been removed by then that the source could no longer be traced. The building contract requires binding arbitration, and the owners filed a demand on July 31. No arbitrator has ruled.
Why it matters: Leak claims on custom homes often turn on who saw the wall before it was opened. Builders: Georgia gives you 30 days to answer a Right to Repair notice, so get your expert on site early. Owners: read the inspection rights in your contract before framing is covered.