Allianz loses bid to throw out £4.2 million claim over cladding and missing cavity barriers
England's Court of Appeal ruled on Nov. 3 that Vivid Housing's latent-defects claim over a 72-flat block in Portsmouth must go to trial, rejecting Allianz's bid to end it early. Vivid says combustible Rockpanel cladding, missing cavity barriers and debris in the walls put the building at risk. Law360 put the claim at £4.2 million.
Vivid owns Collins Place on Victoria Road North, a block more than 18 meters tall. Its housing warranty policy, issued by cover-holder Building LifePlans under authority from Allianz, ran from May 22, 2008, to May 21, 2020. A CBRE façade fire risk assessment in August 2019, 11 years into that term, gave the missing compartmentation its top red rating. Vivid notified the claim on or about May 19, 2020, two days before cover ran out.
The policy pays for repairs when a defect causes a "threat of imminent destruction or physical damage" that calls for immediate remedial work. Allianz argued that no fire was about to start, that Vivid wrote "N/A" on its claim form when asked about urgent repairs, and that the only measure taken was a waking watch. Lord Justice Stuart-Smith, with Lord Justice Phillips and Lord Justice Peter Jackson agreeing, held that Mrs Justice Jefford of the Technology and Construction Court applied the right test in December 2025. She asked whether the fire risk was serious enough and would arrive soon enough. He found CBRE's red rating more telling than the claim form and said a waking watch can arguably count as a remedial step, because it lowers the chance that a fire spreads.
The court did not decide whether Allianz has to pay. Four alleged defects now head to trial: the Rockpanel panels installed with combustible foam insulation, missing vertical cavity barriers, horizontal barriers missing or faulty around party walls, floor-slab edges and windows, and debris left in the cavities. A fifth defect is not part of the appeal. For this application only, Allianz set aside a policy exclusion that covers threats arising from fire.
Why it matters: Latent-defect warranties often outlast the builder. For owners and multifamily contractors, the case shows that a written fire risk assessment and interim steps such as a waking watch can keep a fire-safety claim alive more than a decade after handover.
Sources
- Vivid Housing Limited v Allianz Global Corporate & Specialty SE [2026] EWCA Civ 1389The National Archives (Find Case Law), Nov 3
- Allianz Loses 'Imminent' Fire Risk Appeal Over £4.2M ClaimLaw360, Nov 3
- Vivid Housing v Allianz: Court of Appeal Dismisses Insurance Appeal Over Fire Safety DefectsSolicitor News, Nov 4