Supplier raised the price after you quoted the job: what a contractor can do now and next time

A contractor on Reddit's r/Construction asked what to do when his supplier raised its price after he had already given the customer a number. Who pays the difference depends on whether the customer has signed and on what the contract says about material prices.

Once a fixed-price contract is signed, the risk usually stays with the contractor. Attorney D.S. Berenson wrote in the Journal of Light Construction that most courts in the US and Canada will not release a contractor from a fixed price because materials got more expensive, since higher costs make the job harder but not impossible. A force majeure clause rarely helps for the same reason. Without a clause covering price changes, asking the customer to cover the increase is a request, and the paperwork matters: the bid price, the new price and the supplier's notice.

The tool for the next job is an escalation clause. NAHB's sample version lists each volatile material with its current price, the date and the supplier, and says the owner pays any increase on those items bought after signing, once the builder gives written notice backed by invoices. It also lets the owner walk away if the increases push the contract price past an agreed percentage.

Berenson describes three common triggers: the supplier's invoice, a published price index, or a disclosed bid cost with a threshold, such as an increase of more than 5%. ConsensusDocs offers an amendment that fixes baseline prices for listed materials, and the federal FAR clause 52.216-2 caps upward adjustments at 10%.

Owners accept these clauses more easily when they are narrow. A second JLC article suggests limiting the clause to lumber and a few trades, passing price drops back to the owner and skipping markup on increases. Other options are allowances for volatile items, a shorter window in which the bid stays open, and a fresh price check with vendors right before the contract goes out.

Why it matters: Tariffs and fuel keep moving material and sub prices between the bid and the order. A quote with a short validity window, a last price check with suppliers before signing and an escalation clause for the volatile items decide who pays the next increase.