How MATT Construction built the Samuel Oschin Air and Space Center around Endeavour in launch position

The $450 million Samuel Oschin Air and Space Center at the California Science Center in Los Angeles opened Nov. 13, with Space Shuttle Endeavour standing upright on its boosters and external tank inside a 200-foot steel structure. Crews had to build the hall around a stack that was already in place.

ZGF Architects designed the building and MATT Construction was general contractor, working with structural and aerospace engineers and steel fabricators, ENR reported. The display stack, about 20 stories tall, includes the orbiter, two solid rocket boosters and external tank ET-94, which the science center calls the last flight-qualified tank left. Around it rises a curved stainless-steel structure about 200 feet tall, shaped to the stack and independent of the rest of the 200,000-square-foot center. MATT's project page puts the building at 205,000 square feet on four levels.

The order of work was the hard part. The stack went up while the building was half done, and work on the building kept going around it, MATT chairman Steve Matt told ENR. The contractor lists the problems it had to solve: setting the stack mid-construction, building temporary protection around the shuttle, and erecting the roof diagrid over it with temporary bracing that stayed until the roof could hold itself.

Seismic design took the longest, project director Dennis Jenkins told ENR. Civil engineers know how steel, glass and concrete buildings behave in an earthquake, he said, but those methods do not carry over to an orbiter built to handle weather, not ground shaking. NASA values the stack at $2 billion. Jenkins, a former NASA shuttle program engineer, also oversaw delivery of the other retired orbiters to their museums.

Endeavour's 25th and final mission ended in June 2011, and it is the only shuttle shown in launch position. The new center nearly doubles the museum's exhibit space.

Why it matters: When the owner's $2 billion centerpiece has to go in before the roof, the schedule, protection and temporary bracing plan become the project. The seismic work shows why engineers from different fields need to agree on loads and terms at the start.