Jobsite hacks

Electricians on data center jobs now start before drawings exist, and their first job is information

Data center owners are bringing electrical contractors on before there is a design, says Logan Jacobs of Lighthouse Electric Co. in Canonsburg, Pennsylvania. In an ENR column he lays out what the trade contributes at that stage and what to sort out before a first data center job.

Jacobs, the firm's director of technology, wrote in ENR that his crews join projects with nothing more than an owner's intent: a 300-MW campus, a rough idea of where the data halls go, a list of likely systems. No equipment specs and no architecture. What the electrician offers then is knowledge of crew capacity, equipment lead times and logistics, fed into decisions before they get locked into drawings.

Coordination has changed with it. Trades used to take turns in an area. Now everyone models at the same time in a live file while the design keeps moving, so Jacobs says all parties need one platform that tracks revision history and who changed what. His company moved field layout off paper and highlighters about 10 years ago onto Bluebeam, where markups carry over when a sheet is revised. Field electricians run that work from the office.

The weak point, he wrote, is the handoff. Data passes from the modeling team to the prefab shop as a PDF with a plan sheet and a 3D view, then to the crew installing the assemblies. Any step can be working from an old version. The firm has started a sister company for modular electrical work, which raises the stakes, and Jacobs says tablets in the field still can't carry the model's metadata well.

His checklist for a contractor eyeing a first data center: Is the local labor pool big enough? Are you set up for modeling and prefab? Can the schedule hold? Are project and cost tracking documented? Have you talked to suppliers about material?

Why it matters: Electrical subs chasing data center work are being asked for lead times and manpower numbers before any design exists. Have current gear lead times, a realistic crew count and a version control process for prefab drawings ready before the first meeting.