Jobsite hacks

From 1,100 CFM to 135: where Matt Risinger's Texas house leaked air and how the gaps got sealed

Matt Risinger's crew tested a Texas house at 1.2 ACH50 before insulation, under its own limit of 2 but above the goal of 1. On The Build Show he walks through the leaks and the aerosol sealing that took it from 1,100 to 135 CFM50.

The house already had a fluid-applied air barrier: Prosoco's orange R-Guard covers every sheet of exterior plywood and ties into the foundation. The first blower door test still came in at 1.2 air changes per hour at 50 pascals. Risinger says his company tries to get every house below 1.

The worst spot was a box of conditioned space built out over the garage to hold mechanical equipment, since the roof is only about 3 in 12 and the attic had no room. It sits on AdvanTech with SIP panels for walls, and the trusses cross it, leaving many small gaps where lumber meets. The Aeroseal installer on the job pointed out that garage exhaust gases can reach the return ducts through such gaps. Other leaks were where people seldom look: pans under doors and floor-to-ceiling windows where they meet the slab, triple trusses that pass through the wall to a porch that was switched late from conditioned space to a screened porch, and a hole an electrician cut with a 4 to 5 inch hole saw to pass two thick cables, breaking the crew's one-item-per-hole rule.

Aeroseal fills the house with a fog of latex sealant while a fan pressurizes it. Air rushing out through each crack carries particles that stick to the edges and close the opening. The installer said the system is rated for half-inch holes and in his experience can close about an inch given enough time, and that it is there to catch what people miss, not to make up for sloppy work.

Risinger gives two reasons to chase low numbers in Texas: humid outdoor air carries moisture that can condense behind drywall, and the mild winters keep insects active, so a tight sill line also keeps bugs out.

Why it matters: Test before insulation, while leaks are still reachable. Check door and window pans at the slab, trusses that cross the envelope and every service hole, and hold trades to one penetration per pipe or cable. Aerosol sealing tops off a tight shell; it does not fix big gaps.