Brooklyn building collapse: who is investigating, and what will LERA look at?

New York's Department of Buildings has hired LERA Consulting Structural Engineers to run the independent forensic investigation of the Nov. 11 collapse at 1321 Flatbush Ave. in Brooklyn, ENR reports. Its engineers have been digging test pits and scanning the site with LiDAR and drones since Nov. 20.

The department announced the hire late on Nov. 25 and said it used an emergency procurement. LERA's team is working at the fallen building and at the excavation next door, 2625 Bedford Ave. According to the agency, the review will cover the project's geotechnical report, witness interviews, video evidence and forensic work on site. No cause has been named.

The city has used LERA before. In 2023 the department brought it in, also on an emergency basis, to find what caused the 57 Ann St. parking garage collapse in Lower Manhattan, which killed the garage's manager; ENR reported that contract at just under $1 million. Flatbush is the second big New York construction failure in four months handed to an outside forensic engineer. After two columns buckled on July 7 at the former Pfizer headquarters redevelopment, the city had the owner hire Thornton Tomasetti.

The open question is what was actually in the ground. The approved excavation support plans for the Bedford Avenue lot show soldier piles, walers, rakers and concrete deadmen, plus eight vibration monitors on 1321 Flatbush, four near the first floor and four near the roof, according to ENR. The records made public so far do not show which of those systems were installed and working before the building fell. Asked on Nov. 25 which shop drawings, photos, inspection reports and monitoring logs it had collected, the department would not say, pointing to the investigation it is running with law enforcement.

OSHA records add history for the foundation subcontractor, W.G. NY Construction Corp. On Aug. 25 it was cited for three violations totaling $132,410 after an inspection opened Feb. 26: a willful excavation citation of $115,860, a serious excavation citation of $11,585 and a serious training citation of $4,965. OSHA opened two new inspections of the company on Nov. 12 and Nov. 16, with no citations listed yet. Five of its laborers claim in a Nov. 16 lawsuit that the building lacked proper underpinning, an allegation no court has tested. The collapse killed eight people and injured 18.

Earlier: Brooklyn building collapse: injured workers sue developer, contractors and engineers over shoring

Why it matters: Investigators on this case want the same papers they will want on any dig beside an occupied building: shop drawings, monitoring logs and inspection reports. If your crew installs shoring or monitors, make sure the field record shows what went in, when, and what the readings said.