Ardmore Building Liability Order appeal: why did administrators drop it, and what does that mean for contractors?

Administrators of collapsed UK contractor Ardmore Construction have dropped the appeal against a Building Liability Order because the cost looked too high for the odds, Construction Enquirer reports. The High Court ruling making seven Ardmore group companies liable for Crest Nicholson's £14.9 million award stands.

The case is about Admiralty Quarter in Portsmouth, a 21-storey tower and other residential blocks Ardmore built for Crest Nicholson between 2007 and 2009. Crest alleges combustible insulation, missing cavity barriers and faulty fire stopping. In August 2025 an adjudicator found Ardmore Construction had breached the Defective Premises Act and ordered it to pay £14.9 million. The contractor had entered administration the day before the decision and has paid nothing.

Crest then turned to the Building Safety Act 2022. In April, Mr Justice Constable made two Building Liability Orders: under the first, seven related companies in the Ardmore group share liability for the full £14.9 million, and an anticipatory order covering any future liability found against Ardmore Construction at trial. He also held that an adjudicator's decision counts as a relevant liability under the Act, so a developer does not have to wait for a full trial. Ardmore got permission to appeal in June. The government had been allowed to intervene, and the Court of Appeal hearing was due in December.

In September, creditors approved company voluntary arrangements, run by BTG, for seven group companies including Ardmore Group Holdings, Byrne Properties and Celebration Homes, so the property side could keep trading. Construction Enquirer reported then that other developers could pursue the group for up to £300 million.

A source told the Enquirer the appeal was dropped because of its cost and slim chance of success. Contractors had hoped the Court of Appeal would draw clearer limits on chasing parent and sister companies for an insolvent builder's historic fire safety defects. For now the April ruling is the law on that question.

Why it matters: In the UK, an insolvent trading company no longer ring-fences old building safety claims from the rest of its group. Contractors should know which group companies a BLO could reach and what their insurance and bonds cover for legacy residential work.