Apparent Inc. lawsuits: why is Madison Energy suing the Novato firm over two Hawaii solar projects?

Madison Energy Holdings alleges breach of contract and fraud by Apparent Inc. of Novato, California, its affiliate Apparent Solar and its founder over two Hawaii solar projects, claiming millions. Apparent denies liability and has countersued, the North Bay Business Journal reported.

The first suit, filed in December 2024 in Second Circuit Court in Wailuku, involves solar panels and batteries, 5,350 panels in all, built for Kamehameha Schools on its Pukalani campus on Maui. The school says work started in 2021. Madison, a New York clean energy developer, and a project company claim at least $8.82 million in construction payments, or $9.64 million for delays and underperformance, and point to possible lost tax credits. Apparent wants at least $1.1 million, including a $980,000 final payment Madison held back, plus unpaid operations and maintenance fees. Trial is set for March 2027.

The second suit, filed in February 2025 in Third Circuit Court, covers a planned rooftop solar and battery system at KTA Super Stores' Puainako supermarket in Hilo. Madison alleges Apparent walked off an unfinished job and that the founder passed off a disputed utility approval as valid. It claims at least $7.65 million: $5.32 million in construction payments, $422,025 paid for the project company and $1.9 million to clear its construction loan. Apparent says Madison obstructed its work and seeks at least $1.33 million in lost construction profit. That trial is set for July 2027.

Both cases hinge partly on permission to operate. Apparent says the utilities granted it conditionally in December 2022 and later disowned that approval, and it has pulled Hawaiian Electric, Maui Electric and Hawaii Electric Light into the litigation. In the Maui case, Hawaiian Electric and Maui Electric deny issuing the letter, allege fraud and ask for punitive damages. Madison seeks punitive and triple damages where the law allows. None of the claims has been decided, and Apparent and its lawyers could not be reached, according to the report.

Why it matters: On solar and storage jobs, final payment often waits on the utility's permission to operate. If that approval is later disputed, the contractor's last payment and the owner's tax credits are both at stake, so confirm interconnection approval directly with the utility.