Torsion Care and Torsion Developments liquidation follows Torsion Construction's collapse

Interpath has been appointed liquidator of Torsion Care and Torsion Developments, two more companies in the Leeds-based Torsion group, after contractor Torsion Construction went into administration in July owing more than 500 trade creditors £15.7 million, Construction News reported.

James Clark and Richard Harrison of Interpath took charge of Torsion Care in a creditors' voluntary liquidation on Nov. 9, according to Construction News. The same two became liquidators of Torsion Developments on Oct. 29, a month after the High Court ordered that company wound up on Sept. 29. Interpath also took Torsion Projects into administration on Oct. 16. Clark and Howard Smith have been administrators of Torsion Construction since July.

Torsion Care's statement of affairs, filed this month, lists just over £1 million in unsecured claims from trade creditors and £23.2 million in total unsecured debt, of which more than £18 million is owed to related parties. Chesterfield Borough Council appears to hold the largest trade claim, at £312,184. Brewster Bye Architects is owed £32,400. The filing also shows that Torsion Care guaranteed a £718,270 debt Torsion Construction owes to Derbyshire builder David Ashley Construction. Torsion Care's turnover grew to £68.4 million in the year to March 31, 2025, while its pre-tax loss reached £3 million.

Torsion Construction, which turned over £165.4 million in the year to June 30, 2025, filed its own statement of affairs in October. It lists more than 500 trade creditors with £15.7 million in claims, Briggs & Forrester's £1.3 million among the largest. According to the administrators, the contractor started losing money in its 2026 financial year and used up its cash.

Some of the unfinished work is being handed on. Sandwell Metropolitan Borough Council's cabinet approved Speller Metcalfe this month to complete phases one and two of the Tipton Regeneration Scheme that Torsion Construction left.

Why it matters: Subcontractors owed by Torsion Construction should check whether another group company guaranteed their debt, as Torsion Care did for David Ashley Construction. A guarantee gives a second claim, now in a separate liquidation with its own creditors.