Skanska Georgia data center: what will the $275 million award build, and by when?
Skanska will build a 48 MW, 244,730-square-foot data center in Georgia for an existing client under a $275 million additional award. Work started in November 2026 and is due to finish in October 2028.
Skanska said on Nov. 26 that a client it already builds for has handed it another job in Georgia, this one worth $275 million (about SEK 2.8 billion). The Swedish contractor will book the order with its American business in the last quarter of this year. The company did not name the client or say where in the state the site is.
The project is a new data center rated at 48 MW, with 244,730 square feet of space (about 22,700 square meters). According to Skanska, its scope covers the building shell plus the interior fit-out of technical rooms, support areas and offices. The job also includes a small water treatment building of about 860 square feet. Crews broke ground this month, and the company expects to finish in October 2028.
It is the second Georgia data center award of this kind Skanska has announced this year. In June the company reported a $255 million supplemental contract, also with an existing client, for a building of roughly 245,000 square feet with five data halls, plus site work and underground utilities. That one started in March 2026 and is scheduled for completion in the first quarter of 2028. Skanska has not said whether the two jobs share a client or a campus.
Why it matters: A shell and fit-out job running to October 2028 means electrical, mechanical, interiors and site packages in Georgia over the next two years. Subs in the state should track which of them Skanska puts out to bid.