DFW Terminal F: how will Jacobs fit taxi lanes under the running Skylink train?

Jacobs will redesign parts of the elevated Skylink guideway at Dallas Fort Worth International Airport so two parallel aircraft taxi lanes can run beneath it, keeping the people mover in service throughout, ENR reports. The firm was selected Nov. 24 for the $4 billion Terminal F expansion.

The job is to alter existing Skylink bridge spans rather than move the rail line, according to ENR. Jacobs will work with Innovation Next+, the design-build joint venture on Terminal F, on the structural changes and the order of work that ties the new terminal into DFW's taxiway network. Neither Jacobs nor the airport disclosed the value of the design contract or a schedule for the guideway work.

Airport board records cited by ENR show the work was planned months ago. An April 2 authorization let design of Skylink column changes go ahead alongside utilities, fit-out and apron paving, and raised the joint venture's contract ceiling by $300 million to about $2.06 billion. Work whose price had not yet been agreed was tracked on a time-and-materials basis. A January board action had already added $582 million and 379 days. The joint venture's completion date stands at Aug. 29, 2028.

Terminal F began in November 2024 as a $1.6 billion, 15-gate program and grew to 31 gates for American Airlines after a May 2025 expansion, the Dallas Express reported. On Nov. 3, crews finished lifting six prefabricated Skylink station modules weighing 210 to 310 tons each, every one lifted overnight in about eight hours. The crawler crane for those lifts arrived on roughly 60 trucks. DFW expects the first 15 gates to open in 2027.

Why it matters: Work over a live people mover means night windows, phased spans and tight crane planning. Subs chasing Terminal F packages should expect schedules built around Skylink outages, and part of the joint venture's scope was still unpriced and tracked as time and materials.