Özgür Apartment collapse in Adana: what sentences did the contractors and officials get?

A court in Adana, Turkey, gave the two contractors behind the Özgür Apartment (Özgür Apartmanı) 3 years and 4 months each over its collapse in the February 2023 earthquakes, which killed four people. Three former Seyhan municipality officials got 2 years, 9 months and 10 days each.

The Adana 3rd High Criminal Court convicted contractors Mahmut Alpşar and Murat Alpşar on Nov. 25 of causing the deaths of more than one person through conscious negligence, the Turkish legal term for negligence where the danger was foreseen. The court set four years for each and then reduced it for good conduct, the ANKA news agency reported. Alim Erdoğan, then zoning director of Seyhan municipality, his deputy Sitare Koçoğlu and Gökalp Çubukçu, who ran the municipal mapping section, were each sentenced to 3 years and 4 months, cut the same way to 2 years, 9 months and 10 days.

The block stood in the Güzelyalı neighborhood of Adana's Çukurova district and fell in the second of the two earthquakes that hit southern Turkey on Feb. 6, 2023. According to the prosecutor, expert reports found that the concrete and the reinforcing steel in the building were below the standards set in the regulations, and that construction defects caused the collapse. The same reports put responsibility on the contractors and on the municipal staff who handled the permits.

The prosecutor argued that builders must be taken to foresee deaths when they put up a building with poor materials, even if they did not want that result. He also asked the court to file criminal complaints against other people named in the final expert report. Four of the defendants asked to be acquitted at the last hearing.

Relatives of the four people who died told ANKA the ruling was unjust and said they will appeal. The sentences can still change on appeal.

Why it matters: Expert reports on concrete strength and rebar decided this case, and the court held the permit officials liable along with the builders. In seismic zones, material test records and inspection sign-offs are what investigators read first.