Two truss collapses in Minnesota this year, one fatal: how to brace trusses while you set them
Minnesota OSHA's logs for fiscal 2026 list a worker killed in a fall when trusses collapsed in Lakeville on July 20, and workers who fell with collapsing trusses in Long Lake on April 1. Both cases are open. The truss industry's BCSI guide spells out how to keep trusses standing during erection.
The fatality log, updated Oct. 15, ties the Lakeville death to a framing contractor and a single-family home builder, each with six employees. The serious-injury log puts the Long Lake case under a framing contractor and a commercial builder. Minnesota OSHA has not released findings in either case, so the cause is not established. Occupational Health & Safety reported the updated logs on Oct. 30.
Bracing rules for trusses are set out in BCSI, the guide published by the Structural Building Components Association (SBCA) and the Truss Plate Institute. Its B2 summary sheet names skipped handling and bracing steps as the main cause of accidents during truss erection. The first truss, or the gable end frame, goes up plumb and is fastened to ground braces and the wall before the crane releases it. Top chord temporary lateral restraint goes no more than 10 feet apart for spans up to 30 feet, 8 feet up to 45 feet, 6 feet up to 60 feet and 4 feet up to 80 feet, with extra rows at pitch breaks.
Lateral restraint without diagonal bracing does not hold, the sheet warns. Once trusses two through five are set, the crew adds top chord diagonals or sheathing, web diagonals and bottom chord restraint no more than 15 feet apart, and only then takes down the ground bracing. After that, under the short-restraint method, no more than four trusses go up before the crew stops and braces again. Diagonals go at each end of a run and at least every 10 truss spaces, or 20 feet. Bracing stock is stress-graded 2x4s or approved metal restraint products, with at least two nails at each connection.
Sheathe early, the guide says, and pull only as much temporary restraint as the next sheet needs. For trusses spanning 60 feet or more, it calls for a registered design professional to draw up the temporary bracing plan and supervise erection.
Why it matters: Before trusses arrive, check that ground brace stock, 2x4 restraint material and the truss design drawings are on site, and that the crew knows the restraint spacing for the span. Ground braces stay up until the first five trusses are fully braced.
Sources
- BCSI-B2 Summary Sheet: Truss Installation & Temporary Restraint/BracingSBCA / Truss Plate Institute (via Southern Components), Aug 14, 2013
- BCSI's Step-by-Step Truss Installation ProcessStructural Building Components Association, Sep 12, 2023
- Minnesota OSHA fatality investigations summary, FFY 2026 (updated Oct. 15, 2026)Minnesota Department of Labor and Industry, Oct 15
- Minnesota OSHA serious-injury investigations summary, FFY 2026 (updated Oct. 15, 2026)Minnesota Department of Labor and Industry, Oct 15
- Minnesota OSHA Reports Fatalities and Serious Injuries Across Multiple IndustriesOccupational Health & Safety, Oct 30