Menai Suspension Bridge repairs slip to autumn 2027 after water found on steelwork

Phase two of the refurbishment of Thomas Telford's 200-year-old Menai Suspension Bridge in north Wales will now finish in autumn 2027 instead of spring, the Welsh Government said, after damp steel turned up under the crossing that the planned paint system cannot reliably cover.

The wet patches only became visible once crews stripped the old paint from the underside of the bridge, Construction News reported. Maintenance operator UK Highways A55 has reordered the remaining work while a replacement coating is found that can be applied to damp steel and still meets heritage requirements.

Traffic management on the bridge will be lifted for the rest of 2026. The 7.5-tonne weight limit stays for all of phase two, which also covers repairs to the concrete corbels, recalibration of the land saddle and new lighting.

Deputy transport minister Mark Hooper called the latest slip "unacceptable" and said he has written to the chief executive of Equitix, the infrastructure investor that oversees UK Highways A55, asking for an urgent meeting. It is the second delay this year: in January, then transport secretary Ken Skates moved the finish to spring 2027 after crossbeam bolts needed replacing, MônFM reported at the time.

The bridge closed in October 2022 over safety risks in its hangers. All 168 hangers were replaced by October 2024 in phase one. It shut again in October 2025, when inspections found bolts on the beams under the deck that had to be changed. Last month the Welsh Government said design and environmental work on a third crossing of the Menai Strait would restart.

Why it matters: Blasting old coatings off historic steel can uncover moisture that rules out the specified paint. Owners and painting contractors on similar bridges should test the surface right after stripping and have a moisture-tolerant system ready for approval.