James House sprinkler leaks: judge refuses quick win against firestopper who says the pipe was swapped

A High Court judge has refused to strike out the defence of fire-stopping subcontractor M B Plant, trading as 123 Fire, in a claim over leaking CPVC sprinkler pipes at James House in York, leaving open who caused the leaks.

City of York Council had Robertson Construction Group convert James House into offices and flats for homeless and vulnerable people, starting around 2017. Robertson's mechanical and electrical subcontractor, John Wright Electrical & Mechanical Services (JWE), brought in Premier Mist UK for a water mist fire suppression system and M B Plant for the fire stopping, which it quoted at £15,122.80 and finished in October 2019, according to the judgment.

The drawings called for BlazeMaster CPVC pipe. A different product, Flameguard, went in instead, and M B Plant says it did not learn of the swap until more than three years after it left the site. The firm had tendered a graphite mastic but used Intumastic, which it says suited site conditions better and which it says it checked against BlazeMaster. After leaks were reported in October 2022, a report by Premier and a second report for JWE blamed a sealant that was chemically incompatible with the CPVC. JWE treated the building as unfit to live in, and repairs ran from about November 2023 to February 2024. M B Plant turned down a chance to take part.

JWE argued that M B Plant's November 2024 reply to its letter of claim admitted liability. Judge Kelly of the Technology and Construction Court disagreed in a November 20 ruling. She found the firm had accepted only a duty of reasonable skill and care within its own scope, with no admission about breach or what caused the defects, and said striking out its defence would be "totally disproportionate." The value of the repair claim was not disclosed, Construction News reported.

Why it matters: Firestop sealant that touches CPVC sprinkler pipe has to be checked against the pipe actually installed, not the one on the drawings. Here the pipe was swapped and nobody told the firestopper, and four years later the trades are still fighting over the repair bill.