Heavy-lift drones put 55 tonnes of solar panels on a Bentley factory roof that couldn't take full pallets

Cargo drones, not a crane, lifted more than 55 tonnes of solar modules onto the roof of the Bentley Motors paint shop in Crewe, England, two panels per flight, because the roof could not carry full pallets, The Construction Enquirer reported.

The modules arrived in pallets of 36, each pallet weighing close to a tonne. The paint shop roof had loading limits that ruled out landing whole pallets on it, according to the report. With a crane, a pallet would have hung in the air while the crew pulled off one 27.3-kilogram panel at a time.

Instead the drone shuttled between a controlled loading zone on the ground and a receiving area on the roof, carrying two panels on each trip and delivering them as the installers needed them. At that rate, 55 tonnes works out to roughly 1,000 round trips. The plant stayed in operation during the work.

Push Power Ltd was the main contractor for the solar installation. AutoSpray Systems flew the drones. Andrew Sproson, AutoSpray's co-founder and chief operating officer, said the roof's load restrictions were the real problem the drone solved, since it brought panels up in small batches the roof could bear. Push Power managing director Andy Khan called cargo drones a faster, safer and cleaner way to position rooftop panels.

The companies did not give the job's cost or how long the lift took compared with a crane.

Why it matters: On roofs with tight load limits, small, frequent drops can replace a crane holding pallets overhead. Solar and roofing crews should check the roof's allowed point loads first and price the drone option against crane time and staging.