Fosseway Court, Seaton's unfinished £23 million seafront scheme, goes to auction at a £5,000 guide

Administrators of Fosse Way Court (Management) Limited are selling Fosseway Court, the stalled £23 million apartment scheme on the Esplanade in Seaton, Devon, through Knight Frank Auctions on Dec. 10 with a £5,000 guide price. Work stopped in the summer of 2025.

The lot includes Block 3, a part-built structure meant for 21 one-bedroom flats over parking, the Midweek Herald reported. Its steel frame and concrete floors stand, but the outer walls and roof were never finished. The buyer also takes the freehold of three occupied buildings, all already sold on long leases: Block 1 with 22 flats and three shops, Block 2 with nine flats, and a shop with two flats at 6 Harbour Road. Ground rents add up to about £1,232 a year.

According to the auction particulars, the building as constructed does not comply with its current planning permission, and enforcement action is pending. East Devon District Council approved the scheme in December 2014 and work started in 2017. Foundation problems later forced a redesign and extra piling, costing nine months, a Seaton town councillor said in January. Building costs rose 22%, and lender Shawbrook pulled its funding after reviewing the half-built project, the paper reported.

Gary Shankland and Irvin Cohen of Begbies Traynor were appointed administrators of the company on June 24, 2025, according to a notice in The Gazette. Leaseholders were offered the freehold first under the Landlord and Tenant Act 1987 in June 2026, and none accepted by the August deadline, the particulars say. Garages owned by Block 2 leaseholders can't be reached, because the only way in runs through the unfinished block.

The auction is unconditional: contracts exchange when a bid is accepted, with a 10% deposit of at least £5,000 and a £1,950 buyer's fee. The guide is not a forecast of the final price, and nobody has said whether a sale would restart construction.

Why it matters: A buyer here takes on an exposed frame, pending planning enforcement and leaseholders cut off from their garages, so the real price is the cost to finish and comply. Contractors bidding to complete stalled schemes like this should ask what the planning breach is before pricing the work.