Continental Electric's OSHA fine cut 90% over a 480-volt shock at an Equinix data center site
A federal judge cut OSHA's penalty against Continental Electric Construction Co. from $161,323 to $16,131, ruling that a lockout/tagout violation on Equinix's data center build in Elk Grove Village, Illinois, where an apprentice was shocked, was serious, not willful. The review commission is now reviewing that decision.
The apprentice was hurt on July 3, 2024, while pulling cables to battery cabinets at the building on Lunt Avenue, according to the decision by Judge Joshua R. Patrick of the Occupational Safety and Health Review Commission. Continental was the electrical subcontractor to general contractor Clune Construction. OSHA cited it in November 2024 for willfully breaking the construction rule that requires a tag at every point where de-energized equipment can be powered up again.
Continental had already finished its work in that room and had pulled its locks and tags at the request of Veolia, the owner's commissioning agent, the judge wrote. The next day its general foreman agreed to run the cables as a favor to Equinix, a customer of 20 years, after Veolia's representative said the cabinets would stay dead. A technician from equipment supplier Vertiv then reconnected a wiring harness inside the UPS without telling anyone. When the main breaker was closed, the cabinets went live, and an apprentice touched a 480-volt busbar. Six people from four contractors were working in the room, ENR reported.
OSHA inspector John Cargill testified that ten points needed tags: the main breaker, the harness in the UPS and the breakers on all eight cabinets. Patrick agreed a violation took place but called the willfulness question close. He found Continental had a good safety program that its crews followed closely and little evidence that it acted with plain indifference.
Under federal law the cap is $16,550 for a serious violation and $165,514 for a willful one, ENR reported. The commission has directed the case for review, so the ruling is not final.
Why it matters: In a room shared by several trades, another firm's word that the gear is dead did not satisfy OSHA's tagging rule. Electrical subs should hang their own tags at every energy source before anyone touches equipment, including favor work after their scope is done.