Brooklyn building collapse: cracks on 1321 Flatbush Avenue's facade were visible from 2011

Cracks in the north wall of 1321 Flatbush Avenue, the Brooklyn building that collapsed on November 11 and killed eight people, show up in Google Earth images from 2011 onward, the New York Post reported. City records show no fine or warning about them.

The Post compared street images from August 2011 through March 2026 and found the cracking on the brick north facade spread over those years. That is the wall that came down next to the excavation at 2625 Bedford Avenue. The Department of Buildings has no public record of citing the damage, the paper said.

City inspectors were at the building in May 2019. They wrote 13 summonses for an advertising sign hung illegally on the same north wall, and nine of those remain unpaid, with about $170,000 owed, according to the Post's review of agency records.

Two engineering reports filed with the department before the dig also pointed at the neighbors. A November 2025 geotechnical report by International Geotechnical/Structural Lab, prepared for the new three-story building on Bedford Avenue, said cracks found in the pre-construction survey of nearby buildings should be tracked with monitoring gauges. Quiver League's March 2026 survey for contractor Promont NYC rated the north facade in poor condition with noticeable cracks. The department did not answer the Post's questions on whether gauges were installed.

Buildings Commissioner Ahmed Tigani, appointed by Mayor Zohran Mamdani in January, said in a statement that the investigation is ongoing and the agency wants the responsible parties held to account. Earlier this year, two weeks after Quiver's survey, the department issued a stop-work order at the dig and a $2,500 fine over missing overhead protection for neighbors, the Post reported.

Earlier: Brooklyn building collapse: city-approved dig plan gave the building that fell no bracing

Why it matters: Before you dig next to old masonry, read the pre-construction survey and the geotech report for what they say about neighbors' cracks. If they call for crack gauges, install them, set a reading schedule and keep the logs.