Karachi Baloch Colony building collapse: who was arrested, and how many floors were approved?
Police in Karachi have detained the contractor and a relative of the owner after Wednesday's collapse in the Administration Housing Society near Baloch Colony, which killed at least three people. Officials say the plot was approved for a ground-plus-one building, yet six floors went up.
The toll rose through Wednesday. Rescue 1122 told Dawn that crews pulled three bodies and 14 injured people from the rubble, and the Jinnah Postgraduate Medical Centre confirmed the same count. Sindh Chief Minister Murad Ali Shah said families had reported about 10 people missing, a figure rescuers were still checking. More than 20 workers were on site when it fell, according to Rescue 1122.
Accounts of the arrests differ. East SSP Zubair Nazir Shaikh told Dawn that three suspects were held, among them a contractor and a family member of the owner. ARY News, citing police, put the number at five, including the contractor and the owner's brother, and said raids were continuing.
The permit file shows earlier warnings. East Deputy Commissioner Nasrullah Abbasi told Dawn that the Sindh Building Control Authority (SBCA) approved only ground plus one. When the SBCA ordered work to stop, the owner went to court and won a stay, and the authority then did nothing more, he said. Mayor Murtaza Wahab said the SBCA had planned to demolish the building but was blocked by that stay. Documents seen by ARY News show the plan was approved on March 10, 2026, for a basement and ground plus one, and the six-storey frame went up in about eight months; ARY's sources allege SBCA officials looked the other way.
The cause has not been established. The commissioner's office said 12 other buildings under construction in the society were sealed, and the chief minister ordered checks on nearby structures. He said the owner, consultant, contractor and any officials involved would be held to account. No charges have been announced.
Earlier: Karachi building collapse: six-storey Admin Society block comes down with laborers on site, one dead
Why it matters: A stop-work order meant little once a court stay froze it and the floors kept rising. Police held the contractor along with the owner's relative, so the crew that builds past an approved plan shares the legal risk with the owner.
Sources
- At least 3 killed, 14 injured after under-construction building collapses near Karachi's Baloch ColonyDawn, Nov 25
- Baloch Colony collapsed building was illegally constructed, documents revealARY News, Nov 25
- Baloch Colony building collapse: Contractor, owner's brother among five detainedARY News, Nov 25