Edition
Thursday, November 26
Updated
7:08 PM EST

Fails & scandalsUK

M8 Woodside viaducts: why has Amey's repair bill risen to £185 million?

Repairs to Glasgow's M8 Woodside viaducts by contractor Amey are now expected to cost £175 million to £185 million, up from a top estimate of £152 million, because of a misplaced sewer, a nearby subway tunnel and extra concrete work on two joints. Full eastbound reopening has slipped to early 2027.

Scottish transport secretary Stephen Flynn gave the new figure to MSPs at Holyrood on Nov. 17, Construction News and The Scotsman reported. In August 2025, Transport Scotland was still quoting £126 million to £152 million for the job.

Flynn listed several causes. A sewer turned up where nobody expected it, the Strathclyde Partnership for Transport subway runs close by and has to stay safe, and global supply problems have made procurement harder, he said. The Scotsman reported that the latest slip comes from heavy concrete repairs on two joints. Construction News had earlier reported that inaccurate records of underground utilities held Amey back.

The viaducts are 55 years old and carry Scotland's busiest motorway on columns north of Glasgow city centre. Both carriageways have been cut from four lanes to two since 2021, according to The Scotsman. The eastbound side was due to be finished this autumn and is now expected in early 2027. The westbound side is still scheduled for the second half of 2027, about three years behind the original plan.

Glasgow Labour MSP Pauline McNeill said drivers had been told the road would open this autumn after five years of work, and asked for more regular updates from Transport Scotland. Flynn said he shared her disappointment. A permanent upgrade, or closure of that stretch, is still to follow once the current repairs end, The Scotsman reported.

Why it matters: On old structures the drawings and utility maps can be wrong, and here a misplaced sewer and two worn joints added at least £23 million and a year. Anyone pricing repair work beside live rail or deep services should cost proper site investigation before fixing a finish date.

Sources

More in fails & scandals