Grid United's Wyoming Intertie gets $2.8 billion conditional federal loan to link the US power grids

The Energy Department on Nov. 17 conditionally agreed to lend Grid United up to $2.8 billion for its Wyoming Intertie, a 106-mile high-voltage direct current line of nearly $4 billion that would connect the eastern and western US grids in southeastern Wyoming.

The route crosses Carbon, Albany and Platte counties, from PacifiCorp's Aeolus substation near Medicine Bow to a substation by the Laramie River power station near Wheatland, ENR reported. The line would add about 1,800 MW of transfer capacity in both directions between the Southwest Power Pool and the western grid, which the department says doubles what the two regions can move between them now.

Because the two grids are not synchronized, power has to pass through voltage-source converter stations. Gregory Beard, who heads the Energy Dominance Financing office at the department, told ENR that the converters make up more than half the cost. He said construction could begin around 2030, with completion about 2033.

The commitment is not yet a loan. Houston-based Grid United still has to clear a list of engineering, legal, environmental and money conditions; only then will the department sign final papers and pay out. Beard said the developer holds options on about 97% of the route, but some land rights and regulatory approvals are still outstanding. Grid United is also behind North Plains Connector, a proposed 420-mile line between Montana and North Dakota.

The department puts the savings at up to $39 billion over 30 years across 17 states. Beard said those savings begin only once the line is energized, and ENR noted the department has not released the modeling behind the estimate. He also said more federal loans that include transmission work are coming.

Why it matters: HVDC converter stations are specialty work with long equipment lead times, and this job is not expected to break ground before about 2030. Substation, line and civil contractors in Wyoming should track permits and land rights on the Medicine Bow to Wheatland route.