VolkerFitzpatrick replaces RAF Brize Norton's 3 km runway in 16 weeks
VolkerFitzpatrick rebuilt the full 3 km runway at RAF Brize Norton in Oxfordshire, the RAF's largest station, in 16 weeks, and the first aircraft landed on it on November 13, the Defence Infrastructure Organisation said.
The runway is the main piece of a £180 million upgrade of the airfield, with AECOM providing technical services to the Defence Infrastructure Organisation. Work on taxiways, airfield lighting, drainage and other infrastructure runs until late 2027, the agency said. While the runway was shut from July, the station's aircraft flew from several other airfields.
The new surface combines pavement quality concrete with grooved Marshall asphalt. The DIO chose them to stand up better to heat, and expects the concrete to give the runway well over twice the working life of the old surface. VolkerFitzpatrick senior project manager James Darwent told Forces News that patched sections of the old runway had softened in hot weather, and the new asphalt is built to a much higher specification.
The pace came from round-the-clock shifts. By August, about 500 people were on the airfield and crews had broken out more than 42,250 cubic meters of the old pavement, over 80% of the surface, VolkerFitzpatrick said, with much of it going back into the new runway. By October, crews working 24 hours a day had placed more than 42,000 tonnes of asphalt and pulled over 80,000 meters of cable, Forces News reported.
Why it matters: Airfield closures leave no float. This job shows the setup for a hard deadline: 24-hour crews, old pavement reused in the new runway, and lighting and drainage done in the same closure so the runway reopens once.
Sources
- RAF Brize Norton airfield upgrade passes 42,250m³ breakout milestoneVolkerFitzpatrick, Aug 24
- RAF Brize Norton's £180m runway revamp nears completion, built to withstand extreme weatherForces News, Oct 20
- Aircraft return to RAF Brize Norton after runway replaced in just 16 weeksGOV.UK (Defence Infrastructure Organisation), Nov 18
- RAF, VolkerFitzpatrick and Aecom replace 3km Brize Norton runway in 16 weeks as part of £180M infrastructure projectNew Civil Engineer, Nov 18