WSP sues AECOM in UK court to recover $17 million Frankfurt data center design settlement
WSP wants London's Technology and Construction Court to make AECOM cover all or part of the roughly $17 million WSP agreed to pay Iron Mountain over design problems on a data center in Frankfurt, Germany, ENR reported.
Iron Mountain, the data center developer based in Portsmouth, N.H., hired WSP in 2019 to design a four-story shell holding three data center modules plus offices. The job also covered the office fit-out, 19,000 square feet of data halls and the power and cooling systems. AECOM supplied engineering design on the project to both WSP and Iron Mountain.
Iron Mountain wanted the design frozen before it signed its general contractor in February 2020. By March 2020, when a final set was due, it said the drawings were incomplete and riddled with errors. It said it had to hold back about $20 million in contingency for unfinished design work, where a project that size would normally need less than $1.1 million.
In 2023 Iron Mountain sued WSP for breach of contract in federal court in New York, blaming WSP and its subconsultants for delays and extra cost. WSP denied the claims and turned to AECOM. Discovery ran until January 2026, when mediation produced a settlement under which WSP pays Iron Mountain about $17 million.
The English case, WSP USA Buildings Inc v AECOM Ltd and others (HT-2025-000283), puts the claim at $17.2 million, according to the litigation analytics firm Solomonic, which says WSP blames AECOM's detailed design for the delays. AECOM's answer to the claim has not been made public.
Why it matters: A lead designer on a fast data center job can pay the owner first and then spend years chasing its subconsultant, here across two countries. Check where your subconsultant agreements send disputes and how far their indemnities reach before the design freeze date.