Viña del Mar sinkholes: why did a Chilean court find the state liable for the Miramar Reñaca evacuation?

A civil court in Valparaíso found that Chile's Hydraulic Works Directorate let the Reñaca Norte storm sewer drain more than three times the area it was designed for, then failed to maintain it. It ordered the state to pay about 30 million pesos to an owner evacuated from the Miramar Reñaca building after the 2023 sinkhole in Viña del Mar.

Judge Carmen Gloria Vargas of the 4th Civil Court of Valparaíso ruled that the Dirección de Obras Hidráulicas (DOH), part of the Ministry of Public Works, committed a clear failure of service, La Tercera reported on Nov. 26. The owner had to leave his apartment in September 2023, when the Reñaca Norte collector failed and a sinkhole opened in the dunes near the Kandinsky building. He sought 267 million pesos. The 124-page ruling gave him 30 million for moral damages and 49,800 pesos for direct losses.

The engineering findings carry the case. The collector was approved in 2005, accepted in 2006 and sized for a 45.2-hectare basin. The DOH later let four more collectors tie in (Montemar, Mirador Oriente, Concón-Reñaca and Foresta de la Costa III), adding 116.1 hectares, so the pipe ended up serving 161.3 hectares with no study of its capacity. The approved design also had water moving at 15.5 meters per second on steep runs, and up to 19.95 m/s in later modeling, against a manufacturer maximum of 6 m/s, according to the ruling as reported.

The State Defense Council argued force majeure. The judge rejected it. The system was designed for 10- to 50-year return periods, and the August and September 2023 storms, over 100 mm of rain in under 72 hours with bursts above 30 mm an hour, fell within that range. The collector lasted almost 20 years only because a drought of more than two decades kept big storms away, she found, and the DOH ran no preventive maintenance in the two winters after the Concón master plan took effect in February 2022.

The direct-loss award is small because insurance paid most of his rent: 17 months at 450,000 pesos came to 7.65 million, and his policy's uninhabitability cover had paid 7,600,200. Hundreds of owners in Reñaca and Concón went through evacuations and lawsuits after the collapses, Tiempo de San Juan reported. Whether the state will appeal was not reported.

Why it matters: A storm pipe sized for one subdivision was loaded with four more and never rechecked. Anyone tying a new project into public drainage should ask who verified downstream capacity and flow velocity, and keep those numbers on file: this court treated the missing study as the agency's fault.