Beldev Nominees receivership: who now runs The Markets Residences in Belconnen, and will it be finished?

Receivers from Newpoint Advisory took control of Beldev Nominees, the Canberra developer of The Markets Residences in Belconnen, on November 25. The developer has told buyers the 10-storey block will still be finished, with completion targeted for the first half of 2027.

A receiver and manager from Newpoint Advisory was appointed to Beldev Nominees on Wednesday, November 25, according to ASIC records cited by The Canberra Times. The same firm was put in charge of Canberra Property Development Holdings Pty Ltd that day. Beldev is the joint venture behind the mixed-use project at Belconnen Way and Lathlain Street, next to the Capital Food Market. Icon Construction is the builder and started work in April 2023. The Canberra Times counts 315 approved units; Region Canberra puts the total at 326 apartments.

In an email to buyers seen by The Canberra Times, the developers told buyers the company had not folded and that the receiver and the project team are pushing to get the building done. Region Canberra reported that, with the job this far along, the receivers will aim to get it finished and compliant. Completion had earlier been expected in the first quarter of 2027. A Beldev spokesperson gave no comment before The Canberra Times went to print.

The project has had a rough run. A 2024 dispute between the joint venture partners ended up in the NSW Supreme Court, and in August a former partner was convicted of criminal contempt over a campaign to intimidate the others at the site. He has appealed. This year a group of off-the-plan buyers, working with Adero Law, claimed sales material called windowless rooms bedrooms. The developer denied it. Some buyers told Region Canberra the revised plans hurt their valuations and their ability to get a loan.

Still unknown: who appointed the receivers, what Beldev owes, and what happens to deposits. One buyer told Region Canberra she put down $50,000 and does not know if she will see it again. Under ACT law, a seller cannot cancel an off-the-plan contract under a sunset or delay clause without the buyer's consent or a Supreme Court order.

Why it matters: Icon, its subcontractors and suppliers on a nearly finished 300-plus unit job now deal with a receiver who decides what gets paid and finished. Anyone owed money by Beldev Nominees should check the ASIC notice and the receiver's creditor details.

If this affects you

  • Under the ACT's Civil Law (Sale of Residential Property) Act 2003, a seller cannot rescind an off-the-plan contract under a sunset date or delay clause without the buyer's consent or a Supreme Court order. planning.act.gov.au
  • In the ACT, residential building insurance covers apartment buildings of three storeys or fewer; statutory warranties apply at any height, six years for structural defects and two years for other defects from occupancy. planning.act.gov.au
  • Fair Trading at Access Canberra, on 13 22 81, gives information on buyers' rights under the Australian Consumer Law. planning.act.gov.au