Fails & scandalsPoland

Szczecin Hoża 9: why are evacuated owners suing the city's road agency over a speed bump?

Apartment owners at Hoża 9 in Szczecin, Poland, moved out on Aug. 29 as cracks in the nearly 100-year-old building widened. They are suing the city road and transit authority, ZDiTM, alleging that a speed bump and runoff from the street rebuilt in 2020 shook and undermined it. The trial opened at the Regional Court on Nov. 26.

The owners want the bump removed and the road's rainwater kept off their property, PAP reported. Residents testified that the rebuilt street opened on Oct. 1, 2020, that the first cracks showed in early 2022 and that the damage sped up from 2024. Expert reports they paid for found the building is settling, probably from groundwater flowing in from neighboring lots and from buses and trucks crossing the bump next to their stairwell. One owner said a windowsill had pulled half a centimeter away from the wall.

ZDiTM denies responsibility. Its lawyer told the court the street layout is legal, called the bump a gentle raised section of road and pointed to the residents' own reports, which describe the building as almost completely worn out. Road vibration is probably not the cause, and certainly not the main one, she said. She asked the court to add a 2009 expert report prepared for an attic conversion in the building, and said the agency may consider options other than the bump once the court has examined the case.

Judge Grzegorz Szacoń agreed to widen the suit to cover runoff. The owners' lawyer asked for interim orders to remove the bump and handle the road drainage, which the court has seven days to decide, and for a full study of the building by the AGH University in Kraków. Owners at Hoża 11, the next stairwell, sued ZDiTM a few days earlier, and he asked to join the cases. The claim is valued at 2 million zlotys, the 2023 appraisal of five apartments; a separate damages suit is being prepared. Prosecutors are also looking into the evacuation.

The regional building inspectorate has ordered the owners to shore up the walls by Nov. 30. They have appealed to the administrative court, saying the building is empty and they cannot pay for the work, estimated at 200,000 zlotys. They have already spent about 110,000 zlotys on expert reports and lawyers.

Why it matters: Street rebuilds next to old masonry are where vibration and drainage claims start. Road and utility crews that add bumps, regrade or move runoff near old buildings are better off with a dated condition survey before work begins: courts weigh that record when cracks appear years later.