Valuebuild Homes wins as North Carolina court says a builder's later visit doesn't restart the six-year defect clock
North Carolina's Court of Appeals threw out a Moore County couple's 2025 defect lawsuit against Valuebuild Homes, ruling that the state's six-year statute of repose ran from the 2016 certificate of occupancy, Insurance Journal reports.
The owners hired Value Build Homes in 2015 to build their house in Moore County, and the house got its certificate of occupancy on May 17, 2016. According to the court's account, part of the kitchen floor began to sag within weeks and the builder's crew stabilized it. The owners said the house was never level. In 2023 they told the builder they suspected the house sat on badly sloped ground or a faulty foundation, and in 2024 its workers dug near the foundation and took measurements. The suit, alleging breach of contract, defects and negligence, came in January 2025.
Judge Allegra Collins, writing for the court, said the six years start at substantial completion, which North Carolina courts tie to the certificate of occupancy. A simple repair is not the kind of "last act" that resets the clock, and digging and measuring to look into a complaint is neither construction nor repair, the opinion found. Because the owners said the floor was off from the first day, the court treated the problem as visible in 2016, not hidden.
The claims also failed under the three- and four-year statutes of limitation, the economic loss rule barred the negligence count, and the unfair trade practices claim lacked evidence. The appeals court upheld summary judgment for the builder. Insurance Journal noted the same limit binds insurers that sue contractors in subrogation.
Other states set different windows. Florida cut its repose period from 10 years to seven in 2023, also counted from the certificate of occupancy, and Tennessee uses four years, according to the Gordon & Rees law firm. New York and Vermont have no construction defect statute of repose, the SDV Fenchurch firm said.
Why it matters: In North Carolina, a call-back to look at a complaint does not extend a builder's exposure past six years from the certificate of occupancy. Owners who notice a defect early have to sue inside that window, so the CO date on file decides who can still be sued.