DPR Construction puts generator lead times near 56 weeks as data centers lead 2027 spending

DPR Construction's fourth-quarter Market Conditions Report says its supply chain team sees lead times of about 56 weeks for generators, 37 weeks for switchgear and switchboards and 66 to 132 weeks for some medium-voltage equipment, while the forecasts it cites have data center spending up 25% in 2027.

The general contractor's report, by Roel Aguilar and Tim Jed, argues that one national number tells an owner little about a given job. It cites the American Institute of Architects' July consensus forecast: nonresidential building spending down 0.3% in 2026 and up 3.0% in 2027. AIA expects data center spending to climb 33% this year and 25% next year. Without data centers, commercial spending drops 1% in 2026 and gains 1% in 2027.

DPR says its lead times are internal estimates that vary by project and supplier. The questions it puts to owners: does the specified product have a manufacturing slot, which approvals have to come first, and how does the delivery date fit installation and startup? An early release can protect a milestone. It can also commit the owner before scope and design are final.

On labor, the report cites the September survey by the Associated General Contractors of America and NCCER. Of the firms surveyed, 87% had openings for hourly craft workers, and 88% of those said the jobs were as hard or harder to fill than a year earlier. Still, 37% had cut headcount by at least 5% over the year. Dodge's Momentum Index rose 2.4% in September, with institutional planning up 9.4% and commercial planning down 1.3%.

Demand for data centers looks real, DPR says, quoting CBRE: 7,481 megawatts were under construction in eight primary North American markets in the first half of 2026, and 80.4% of it was preleased. MSCI found that 52% of US data center projects in development sit in counties where earlier projects were withdrawn or restrictions were added. Construction Owners, in its summary of the report, noted a proposed copper tariff of 15% from Jan. 1, 2027, rising to 30% in 2028.

Why it matters: Electrical and mechanical subs bidding 2027 work should confirm manufacturing slots for generators, switchgear and medium-voltage gear before committing to a schedule, and price copper-heavy scope with the proposed tariff in view.