Toulouse metro line C reuses 80% of more than 6 million tonnes of tunnel spoil, from bricks to quarry fill
Tunnel boring machines and station digs on the 21-kilometer underground stretch of Toulouse's metro line C have removed more than 6 million tonnes of soil, and project engineer Tisséo Ingénierie says about 80% of it is being reused, above the 70% French law requires.
La Dépêche du Midi reported the figures on Nov. 24. The spoil waits in large storage bins at the three sites where the machines were launched: Colomiers Gare, Ponts-Jumeaux near the ring road, and La Vache. Each batch is tested for contamination before trucks take it away.
Part of it becomes brick. At the Bouyer-Leroux plant in Colomiers, a manager estimated early in the job that line C spoil would yield about 3 million bricks, enough for 3,750 houses. Other loads go into roads and interchanges, among them the Verfeil ramp onto the A69 toward Castres, or back into line C itself. The rest fills old gravel pits that are being turned back into natural areas or farmland, as at the Gravière and Bordeneuve lakes, according to Tisséo Ingénierie.
At the face, the cutterhead grinds the ground, a screw conveyor draws the muck out of the chamber and a belt carries it to daylight. Three of the line's five tunnel boring machines are still digging. Jeanne-Marvig, launched from Colomiers Gare, reached Airbus's Saint-Martin-du-Touch site on Nov. 16 and has about 600 meters to go to the Laporte shaft beside the airport runways, where the machine from Ponts-Jumeaux is also headed. The machine from La Vache has passed Toulouse-Lautrec station and will stop at Raisin.
Toulouse Métropole says line C, which will run from Colomiers to Labège, is due to open to passengers at the end of 2028.
Why it matters: Hauling and dumping spoil is a large cost on any tunnel or deep excavation. Toulouse shows where clean, tested soil can go instead of a landfill, from a brick plant to road fill and pit reclamation, and what it takes to beat a 70% reuse requirement.