Halo tower Sydney: how did the troubled A$1.8 billion timber skyscraper get to construction?
The 55-storey Halo hybrid timber office tower in Sydney's CBD reached early works after Cbus Property and Milligan Group formally started their 50-50 joint venture and signed Multiplex as builder, Mingtiandi reported. Completion is now set for 2031.
The partners said this week that the project on the corner of Hunter and Pitt streets has the approvals it needed and a signed construction contract, according to Mingtiandi. The tower is budgeted at A$1.8 billion (about US$1.2 billion), and its developers describe it as one of the tallest hybrid timber buildings in the world. When Cbus agreed to buy half the site in September 2025, the goal was completion early in 2030, with Multiplex already on board under an early contractor involvement agreement, The Urban Developer reported at the time.
The design combines a hybrid timber structure with a glass facade that generates solar power. The site was assembled from five buildings and 72 separate titles, and it includes the heritage-listed Pangas House, which Multiplex said is built into the design. CBRE puts the floor area at about 44,000 square meters (roughly 474,000 square feet). The building is planned as fully electric with a 6-Star Green Star target, and it will connect straight into the Hunter Street station on Sydney Metro West, which the partners expect to open in 2032.
The project needed a rescue to get this far. Merricks Capital arranged a A$465 million loan in 2023 for the land purchase, a planned sale to Lendlease fell through, and second-ranked lenders issued a default notice, Mingtiandi reported, citing The Australian Financial Review. KPMG was later appointed administrator of the site-owning companies, and creditors approved a deed of company arrangement over objections from unsecured creditors. A group of 22 former landowners, who are owed part of their sale price when the project is finished, then took the arrangement to the Federal Court.
Multiplex, a unit of Japan's Obayashi, has built more than A$3 billion of projects with Cbus Property, including 435 Bourke Street in Melbourne. The partners did not say what Cbus paid for its half.
Why it matters: A signed builder on a 55-storey hybrid timber tower puts mass timber at real height into a lender-backed office job, and contractors will watch how it is sequenced and insured. The Federal Court challenge by former landowners is still the open risk.