Boston North Station drawbridge replacement: how did Skanska cut a bridge from the $1.3 billion job?

The Skanska and Koch joint venture swapped the MBTA's plan for three new lift bridges and a temporary span for two lift bridges with three tracks each, a change Skanska says saved Massachusetts $140 million on the $1.3 billion North Station Draw One replacement in Boston, ENR reported.

Draw One carries every commuter rail line north of Boston, plus Amtrak's Downeaster, across the Charles River into North Station. About 11 million passengers and 200 trains a day use it, and it opens for nearly 3,000 boats a year. Its two rolling bascule spans are 95 years old and carry four tracks. They will be replaced by two vertical lift spans carrying six tracks, along with eight miles of track, 67 specially built turnouts and crossovers, new signals with positive train control, a new Tower A control building and a new platform that takes the station from 10 to 12 tracks.

The MBTA's concept called for a first lift bridge and a temporary rail bridge to the west, then demolition and two more bridges to the east. Paul Pedini of Skanska USA Civil told ENR his team found no precedent for that kind of temporary rail bridge, and building a third span between two live ones left no room to work. Using virtual design and construction models, the team and designer VHB settled on two bridges. The MBTA put no cap on alternative technical concepts and held twice the usual number of confidential meetings with bidders. Karl Eckstrom, the agency's deputy chief of structures, said Skanska's bid scored higher on technical merit before prices were opened.

The design-build work began in May. Trains must run around the clock, and river closures are limited to five days over a schedule of about six and a half years. Crews will place hundreds of foundations through the wreckage of older bascule bridges that burned in 1984. One new bridge is due in service about 3.25 years after the start. A $472 million federal grant from 2024, the largest project grant the MBTA has received, helps pay for the work.

Why it matters: An alternative technical concept removed a temporary bridge and a third span and, by Skanska's count, $140 million. Subs pricing track, signal or foundation work here should plan around 24/7 rail service and a five-day limit on river closures.