Speller Metcalfe to finish Torsion's abandoned Tipton council homes as costs top the original budget

Sandwell Council has picked Speller Metcalfe to complete 55 affordable council flats in Tipton, West Midlands, left part-built when Torsion Construction went into administration this summer. A council report warns that finishing them may cost more than the money set aside, Construction News reported.

Torsion won a £13.2 million contract for the homes last year, Construction News reported, and broke ground with the council in October 2025 on cleared sites on both sides of Union Street. Its collapse left what a council report described as a partially built site. The council's cabinet voted unanimously to appoint Speller Metcalfe for the first two phases of the Tipton Regeneration Scheme after a competitive evaluation on the Constructing West Midlands framework, council leader Ray Nock said. He noted the firm has taken over jobs from failed contractors before.

Officers told councillors that hiring through the framework was the only realistic way to keep the scheme moving and to cut the risk of having to repay grant money. The wider Tipton project has £20 million of government money from the Local Regeneration Fund plus council funds, and also includes 15 homes in the former Conservative Club on Union Street and work along Owen Street, according to the council. Without a new builder, the report said, the council could miss grant conditions and delivery deadlines.

Completing the homes may need more than the original budget, the report warned. Officers are weighing the Housing Revenue Account, outside grants and existing regeneration capital to cover the gap. No value has been published for Speller Metcalfe's contract. Other former Torsion jobs are also being reassigned: north London contractor AC1 was named in September to finish a £26 million residential tower, Construction News reported.

Why it matters: A public owner restarting a job after its contractor fails pays twice: re-procurement time and a new price for half-built work, under grant deadlines. Subs owed money by Torsion stay creditors in its administration, and the work under Speller Metcalfe is a new contract.