Borough Yard: Sisk to get £36.5 million enabling job as Wirral's costs rise by £21 million
Wirral Council has agreed in principle to give John Sisk & Son a £36.5 million contract for the next enabling works at Borough Yard, the 1,600-home scheme on old railway sidings and gasworks in Birkenhead, after site surveys pushed the package £20.7 million over budget, Place North West reported.
The council backed the deal on Wednesday, Nov. 18. Sisk will remediate and engineer the ground for the first two phases, build the Mollington Link to the Hind Street active travel corridor and deliver the Waterloo Place section of the Dock Branch South linear park. The contractor already ran the site investigations under a 2025 pre-construction agreement.
Several pieces sit outside Sisk's contract: moving the gas works, realigning the Kings Square link, drainage work with United Utilities and the rest of the linear park. Place North West reported those are estimated at another £31 million and that the full package now runs £20.7 million above the £57.1 million budget. The council plans to pay for the Kings Square link and the linear park from its £29 million share of the city region's transport money. With those two items taken out, the programme costs £66 million, still £8.9 million more than budgeted.
The scheme, formerly called Hind Street, covers 65 acres and includes a park and 650,000 square feet of commercial space. Wirral is developing it with ION Developments and Picture This, and it has £52.1 million from the Liverpool City Region Combined Authority and Homes England. At the same meeting the council agreed a £2.9 million development management agreement under which ION will run the enabling works for the council. Construction Enquirer reported last year that the first housing phase was due to start in 2027.
Why it matters: Surveys of an old gasworks added about a third to the enabling budget before a single home went up. Anyone pricing remediation on brownfield housing should budget for what the investigations find, and Merseyside groundworks subs should watch Sisk's packages.