Interstate Bridge Replacement gets one design bid, from a Kiewit-led team, and lawmakers question the cost

The $14.4 billion program to replace the I-5 bridge over the Columbia River between Portland and Vancouver, Wash., drew a single design bid in late September, from Columbia River Constructors, a joint venture of Kiewit Engineering Group, Guy F. Atkinson Construction and Traylor Bros., the Oregon Capital Chronicle reported.

Kiewit would lead the team. The program plans to use progressive design-build, which brings the owner, designer and builder together early in design. John White, a Washington transportation official, told the joint Oregon-Washington legislative committee on Monday that the method gives more cost certainty and open pricing. Washington Gov. Bob Ferguson has said the construction contract will be awarded next year and that traffic could use the new bridge by 2035, about two years later than earlier planned.

Several lawmakers asked how the states would hold the team to a price. Committee co-chair Rep. Ed Orcutt, R-Kalama, said a lone bidder can set its own number and the states either pay it or lose the project. Oregon Rep. Thủy Trần and Sen. Bruce Starr raised the same concern. Others, including Oregon Rep. Susan McLain and Washington Rep. Jake Fey, said few firms can take on a job this size and noted that two interested firms chose to team up.

Kiewit's recent record drew most of the questions. Its I-205 Abernethy Bridge job in Oregon City is more than two years behind schedule, and the estimate has grown to about $800 million from $250 million in 2018, KGW reported. In April, Maryland dropped Kiewit from the second phase of the Francis Scott Key Bridge rebuild after Gov. Wes Moore called its price and schedule unacceptably high. Kiewit also got negative marks in four straight annual ODOT contractor reviews since 2022, according to the Daily Journal of Commerce. Kiewit spokesperson Bob Kula said the company does not comment on pursuits and stands behind its record.

The program's own estimate has already roughly doubled, from up to $7.5 billion in 2022 to about $14.4 billion this March.

Why it matters: With one team bidding, the states negotiate the design price without a competing number on the table. Subs, suppliers and DBEs in the Portland-Vancouver market will be dealing with one prime team for years; the construction contract is due next year.