How This Old House lowered a basement floor without undermining a fieldstone foundation
In a video posted Oct. 30, This Old House showed a crew deepening the basement of an old house whose fieldstone walls have no footings. Before pouring the new floor, the crew cast a reinforced concrete buttress wall along three sides so the stone would not be undercut.
The sequence, as the video presents it: dig down, form and pour the reinforced buttress against three of the walls, then lay a vapor barrier, a layer of sand and 6x6 welded wire mesh, and pour the slab. The buttress was cast with a ledge that will later hold the framing for finished walls.
Builders have described this risk for years. Stone walls built without footings rest on the soil under them, and once the soil beside them is disturbed, moving water can carry away fines and weaken that support, a builder explained in a Fine Homebuilding forum thread on deepening a stone basement. Another contributor described the local practice of leaving 6 to 10 inches of undisturbed soil against the wall and pouring a kneewall to hold it in place. A third reported that the weight of fresh concrete pushed in a section of rubble wall about 4 feet wide and 5 feet high under a basement window.
For the slab itself, check which code edition is in force. The 2021 International Residential Code raised the under-slab vapor retarder from 6-mil polyethylene to a 10-mil product meeting ASTM E1745 Class A, with laps of at least 6 inches, according to vapor barrier maker Stego Industries. Stego adds that generic poly sheeting does not meet that standard at any thickness.
Why it matters: Lowering a floor beside stone walls with no footings can undermine the house. Plan the buttress or kneewall before digging to full depth, and confirm whether your jurisdiction requires the 2021 IRC's 10-mil Class A vapor retarder under the slab.
Sources
- Deeper basement with stone foundationFine Homebuilding, Jan 17, 2003
- Your Guide to Navigating the IRC Building Code Changes to Vapor RetardersStego Industries, Apr 24, 2024
- Pouring a New Concrete Floor | This Old HouseThis Old House (YouTube), Oct 30