Tata Projects vs Noida airport: why did the Delhi High Court reject its bid to recover ₹329 crore in guarantees?
The Delhi High Court on Nov. 26 dismissed Tata Projects Limited's petition against Yamuna International Airport Private Limited (YIAPL), developer of Noida International Airport at Jewar. The court said the ₹329.10 crore YIAPL cashed from Tata's bank guarantees is a money dispute for arbitration, with no fraud alleged and no harm that can't be undone.
YIAPL hired Tata on June 8, 2022 under two EPC contracts for phase 1 of the airport: terminal works for ₹1,892.42 crore and airside, landside and utility works for ₹2,689.60 crore, with completion due on Nov. 23, 2024, according to the judgment. Disputes followed. Tata claimed ₹1,112.87 crore and YIAPL counterclaimed ₹436.72 crore.
A settlement signed on Feb. 25, 2026 set a one-time payment of ₹500 crore to Tata and moved the completion milestone to July 31, 2026, with 60 days of grace to Sept. 29. Tata missed it, the court recorded. YIAPL then cashed two State Bank of India performance guarantees worth ₹229.10 crore and a ₹100 crore advance guarantee from Union Bank of India. Two IDBI Bank retention guarantees, worth about ₹190.8 crore together, had not been called.
Tata told the court that YIAPL paid only ₹100 crore of a ₹200 crore first installment, that Tata spent ₹167.68 crore of its own money on the job between June and October, and that delay damages, charged at 0.15% of the contract value for each week as the settlement allows, would total about ₹64.45 crore. It also argued the advance guarantee should have lapsed once the advance was repaid. YIAPL answered that it released ₹243 crore in all, that later installments depended on milestones Tata never reached, and that the airport works are still unfinished.
Justice Tushar Rao Gedela wrote that even if the calls broke the contract, that question needs a full inquiry by an arbitral tribunal. Money from a cashed guarantee can be ordered back if Tata wins there, he held, so the loss is not irretrievable. The petition was dismissed. The ruling refers to a tribunal still to be formed.
Why it matters: Indian courts almost never stop an owner from calling an unconditional bank guarantee without fraud or harm money can't fix. Before signing a settlement tied to new milestones, check what each guarantee secures, when it lapses and whether the owner may call it for any shortfall.