STRABAG starts widening 65 km of Poland's A2 between Warsaw and Łódź in a €158 million job

STRABAG has begun work on all three of its sections of the A2 motorway between Warsaw and Łódź, adding lanes along about 65 km for GDDKiA, Poland's national road agency. The three contracts are worth about €158 million, or roughly 697 million zloty, the company said on November 19.

The motorway grows from two lanes each way to three, and to four each way near Warsaw, according to STRABAG. Section D runs 17.2 km from Konotopa to Grodzisk Mazowiecki. Section B covers 21.8 km from Łyszkowice to the boundary of the Łódź and Masovian regions, and section C carries on for 25.5 km to the Grodzisk Mazowiecki interchange.

Besides the new lanes, crews will rebuild the existing pavement, repair bridges and other structures, and replace guardrails, noise walls, lighting and traffic control systems. The road stays open the whole time, with at least two lanes running in each direction. Sections B and D are due for completion at the end of 2027 and section C in early 2028.

Reclaimed asphalt is central to the mix designs. STRABAG plans 35% recycled material in the binder and base courses and 20% in the wearing course. It says it upgraded three asphalt plants to hot-recycle larger volumes of millings and pairs the higher recycled content with foamed bitumen. GDDKiA wants the widened road to power its lighting, weather stations and other equipment from renewable sources, and solar panels, battery storage and a wind turbine are planned along the route.

Why it matters: Roughly €2.4 million per kilometer to add a lane each way under live traffic is a useful benchmark for US highway estimators. The 35% and 20% recycled asphalt shares show how far a large European contractor is pushing reclaimed material on a busy motorway.