Sternbrücke Hamburg: how did Mammoet move a 3,700-tonne rail bridge into place in under a day?
Mammoet built Hamburg's new Sternbrücke on a yard 500 meters away, then carried the 108-meter, 3,700-tonne steel span down a city street on self-propelled modular transporters overnight on July 30 and 31, turning it 45 degrees and lowering it onto its abutments by 7 a.m.
The bridge carries the Verbindungsbahn, the rail link between Hamburg's main station and Altona, over the Stresemannstraße and Max-Brauer-Allee junction. About 1,000 long-distance, regional and S-Bahn trains use it on an average day, according to Deutsche Bahn. Building the new span in place would have shut that junction for years, Global Construction Review reported this week as Mammoet released photos of the job. The closure lasted about six weeks.
Crews spent 14 months assembling the span on the Brammer site beside Max-Brauer-Allee. The space was so tight that parts had to arrive in the order they were needed, Mammoet project manager Lars de Haas told GCR. Mammoet assembled its transporters in two stages: it jacked the bridge from 2 meters to 4.5 meters to roll the first set under, then added the second. The two configurations had 272 axle lines in all, with 16 climbing jacks rated at 500 tonnes each. On the street, a second jack-up of 1.5 meters lifted the span high enough to clear the new abutments.
Deutsche Bahn said the move started on July 30 at no more than 1 km/h, with the bridge riding 6 meters above the road on 1,088 wheels. In places it passed within 30 centimeters of the buildings on each side, according to GCR. It reached its final position at 3 a.m. on July 31 after about seven hours, and sat on its abutments four hours later.
Mammoet started the feasibility study in 2017 and finished its last revision in 2023, using 3D scans of the route. After the lift, crews laid about 4 kilometers of rail, 3,000 sleepers and 8,000 tonnes of ballast and rebuilt the overhead line and signaling. Trains returned on Aug. 31, Deutsche Bahn said. It used the same closure for work on the new Altona station and two other rail bridges.
Why it matters: For owners and bridge contractors weighing accelerated bridge construction on a busy urban rail line, Hamburg shows the price of short closures: a laydown yard next to the site, six years of move planning and just-in-time deliveries.
Sources
- Neue Sternbrücke wird eingehoben: Transport des Bauwerks zum Zielort ist gestartetDeutsche Bahn, Jul 30
- Hamburg: Sternbrücke nach Transport erfolgreich eingehobenDeutsche Bahn, Jul 31
- Hamburger Verbindungsbahn wieder frei: Züge fahren über neue SternbrückeDeutsche Bahn, Aug 30
- Mammoet installs crucial Hamburg bridge in under 24 hoursGlobal Construction Review, Nov 27