Sault Ste. Marie port gets C$250 million from Canada and Ontario for berths, a rail yard and industrial land

Ottawa and Ontario have committed C$250 million (about US$174.5 million, as ENR reported it) to a new multimodal port in Sault Ste. Marie, Ontario, which HOPA Ports and the city plan to build on about 243 acres along the St. Marys River, with major construction set for 2029.

Transport Minister Steven MacKinnon announced C$125 million from the federal Trade Diversification Corridors Fund on Nov. 20, and Ontario Transportation Minister Prabmeet Sarkaria said the province plans to lend another C$125 million, according to HOPA Ports, the Hamilton-Oshawa Port Authority. The city has approved up to C$15 million of its own, on condition that the federal and provincial money came through.

The plan calls for Seaway-draft berths, a rail transload yard, cargo-handling areas, roads, utilities and lots ready for industrial tenants on underused industrial and brownfield land. HOPA expects more than 2.4 million metric tonnes of cargo a year once the port runs. ENR cited Ontario's estimate of about 2.65 million short tons a year, against roughly 691,600 short tons today, and reported that it would be the first public port open to many users between Thunder Bay and southern Ontario.

No construction contracts have been announced. HOPA's schedule puts land agreements, Indigenous partnerships, environmental and technical studies, regulatory review and detailed design in 2027. If approvals come through, site preparation could start in 2028, with the main marine, rail, road and utility work in 2029 and full buildout in 2031. HOPA puts engineering and construction employment at about 1,270 jobs.

The port will run separately from Algoma Steel, which will be able to use it on terms still being negotiated, ENR said. HOPA and the city say they consulted more than 40 companies in manufacturing, mining, forestry, agriculture, transportation and marine services. Once the port is fully running, HOPA projects that activity around it could support up to 4,750 direct and indirect jobs a year.

Why it matters: Marine, rail and heavy civil firms in Ontario and nearby Michigan get a long runway here: design and studies in 2027, site prep possibly in 2028 and the big marine and rail packages in 2029, all subject to approvals.