Portal North Bridge fully opens as Amtrak and NJ Transit retire the 116-year-old Portal Bridge
Every Northeast Corridor train now crosses the Hackensack River in Kearny, N.J., on the new Portal North Bridge, after a weeks-long cutover moved the second track off the 1910 swing bridge. NJ Transit trains were back on regular schedules on Monday, Nov. 16, CBS News reported.

The old Portal Bridge entered service for the Pennsylvania Railroad in November 1910. According to Amtrak, it carries more than 450 Amtrak and NJ Transit trains and about 200,000 riders a day between Newark and New York Penn Station, and its two-track swing span often failed to close properly after opening for boats. Its replacement is a fixed span more than 50 feet above the water that, counting the approaches, runs nearly 2.5 miles along the corridor. Skanska and Traylor built it as a joint venture, with WSP USA, SC Engineers and Malick & Scherer on the design side.
The first track on the new bridge opened to trains in March 2026. Moving the second one meant shifting Amtrak's overhead wires and electrical systems, and riders lived with adjusted schedules through an outage that Amtrak listed as running from Oct. 9 to Nov. 16. Downed power lines on Friday, Nov. 13, pushed some trains onto the new bridge three days ahead of plan, CBS said. Gov. Mikie Sherrill took a ceremonial first ride the day before.
The job is not finished. Amtrak expects to complete the project in 2027, once the old bridge is demolished. Funding came from Amtrak, the Federal Transit Administration's Capital Investment Grant program, the New Jersey Transportation Trust Fund and the New Jersey Turnpike Authority.
Portal North is part of the Gateway Program, a program meant to give trains twice today's rail capacity between Newark and New York. NJ Transit chief executive Kris Kolluri called the past four weeks hard on riders, and the agency still asked them to check train times.
Why it matters: Demolishing the old swing span in the river is the next contract on this site, with project completion set for 2027. The cutover is a template for live-corridor work: weeks of reduced service and a wire transfer before trains return to full schedules.
Sources
- Portal North BridgeAmtrak, Nov 16
- New Portal North Bridge fully opens after years of constructionCBS News, Nov 16