Megaprojects

Philadelphia's 30th Street Station finishes its first restoration phase as SOM and Gilbane clear the main hall

SOM says the first phase of the renovation of Philadelphia's William H. Gray III 30th Street Station is complete, with ticketing and bag drop moved out of the main hall into a little-used north wing. Gilbane is building the $550 million project while trains keep running.

Phase one restored the beaux arts main hall and kept its art deco chandeliers, Dezeen reported. The biggest move was functional: ticket counters, baggage drop-off and other services left the hall for the north wing, which freed floor space for seating and passengers walking through. SOM also redid the food and retail area in the south concourse with Nelson Worldwide, and the upper floors hold new Amtrak offices.

The South Concourse reopened the week of Nov. 12 with new seating, charging outlets and rebuilt public restrooms, PhillyVoice reported. Its bronze and brass storefronts were restored. In the main hall, crews have mostly finished cleaning the ceiling panels and limestone walls, and Gilbane is cleaning the light fixtures and changing bulbs. Shops are working out of modular kiosks for now, and new food and retail will open in stages over the coming months. Large parts of the building are still construction zones.

The station is run under a public-private deal. Plenary Infrastructure Philadelphia signed with Amtrak in 2021 and will operate and maintain the building through 2071, with Gilbane as design-build contractor. ENR reported in 2024 that the finish date had slipped from 2025 to 2027, and the project's own site now says construction continues through 2028.

The building is on the National Register of Historic Places, so the plan needed a Section 106 review under federal preservation law. Amtrak calls it the third-busiest station in its network, with more than 3 million riders in 2022, and SEPTA and NJ Transit trains stop there too.

Why it matters: Keeping a listed station open through a $550 million rebuild means moving functions out before restoring a space, phasing every area and ordering long-lead items early. Gilbane issued early bid packages for that reason. Subs chasing station or historic work should price in work around passengers, tight staging and pres