Megaprojects

Oceanwide Plaza graffiti is mostly gone as KPC Square works to close its purchase of the LA towers

Crews have removed most of the graffiti from Oceanwide Plaza, the three unfinished towers at 1101 S. Flower St. in downtown Los Angeles, city officials and buyer KPC Square said Nov. 12. The $470 million purchase out of bankruptcy still has to close before construction can restart.

KPC Square LLC is a joint venture of the KPC Group and Lendlease, the general contractor on the towers until work stopped in 2019, when Beijing-based Oceanwide Holdings could no longer pay for it. Affiliates of Oceanwide's senior creditors own the venture, according to Hilco Global, the court-approved broker. U.S. Bankruptcy Judge Deborah J. Saltzman confirmed the liquidation plan for Oceanwide Plaza LLC on July 20, after the city and county of Los Angeles withdrew their objections.

The graffiti was the city's price. Taggers covered at least 25 floors in early 2024, and the cleanup deal let the sale go forward. Work began in July, crews finished the 250 balconies on Oct. 20, according to the Los Angeles Business Journal, and touch-ups on some windows continue, MyNewsLA reported. KPC Group chairman Kali Chaudhuri said the cleanup was about rebuilding confidence in the site.

Money is the harder part. The buyers say they expect to spend hundreds of millions of dollars more on the 1.5 million-square-foot complex and are still working out a feasible way to restart. In a video released Nov. 18, The B1M estimated the cost of finishing to the original design at about $800 million. It said KPC Square accepted a six-month window to close, and that a backup bidder could take the property if the money is not in place by early 2027. The channel also noted that structural problems could still turn up in a frame that has stood open since 2019.

The design calls for a 677-foot tower with a Park Hyatt hotel and serviced condos, two 530-foot towers with 504 condos, and a retail base. Los Angeles wants the site finished before the 2028 Olympics, when the arena across the street hosts gymnastics and boxing, The B1M said.

Why it matters: Restarting a frame idle since 2019 means structural and envelope surveys, new permits and a new buy-out of most trades on a downtown block. LA subs and suppliers should watch for the sale closing and KPC Square's restart schedule, which will decide when bid packages go out.