Myitnge (Dokhtawady) Bridge replacement 78% done, set to open in March 2027 after quake collapse
Myanmar's Ministry of Construction says the new four-lane Myitnge (Dokhtawady) Bridge on the Yangon-Mandalay Expressway is 78% complete and should open to traffic in March 2027, replacing the 700-foot span that fell in the Mandalay earthquake of March 28, 2025.
The old bridge, built in 1999, collapsed completely in the quake, the state-run Global New Light of Myanmar reported. Since then, expressway drivers heading for Mandalay have left at the Saga-Inn roundabout at Milepost 352/6 and continued on the six-lane Yangon-Toungoo-Mandalay Highway toward Paleik.
The ministry put the replacement on a new line 90 feet upstream of the fallen span, at Milepost 358/1-3. The new bridge is 1,000 feet long. Crews have finished the bored pile foundations and the piers, the precast prestressed concrete girders on the approach spans, the reinforced concrete deck slabs and railings, and the approach embankments.
Work now centers on installing steel box girders and laying concrete pavement on the approach roads. The ministry expects all major structural work on the crossing between the Yangon and Mandalay banks to be done by the end of February 2027. Asphalt paving on the bridge and its approaches, street lights and finishing work follow in March, before traffic is let on.
The report did not give the cost of the job or name the contractor.
Why it matters: The rebuild follows a familiar disaster-replacement sequence: a new alignment upstream of the wreck, precast girders on the approaches and steel box girders at the river. It puts a number on recovery time: about two years from collapse to traffic on a 1,000-foot crossing.