Midland Construction sues Baystreet's developer directors for €12.8 million after winning arbitration
Midland Construction and Engineering, a builder from Kells, Co Meath, is suing the directors and shareholders of Baystreet Ltd, among them developers John McKeon, Brian Kennedy and Liam McSharry, for almost €12.8 million over a 44-apartment job in Clontarf, The Irish Times reports. Baystreet is in liquidation.
Baystreet hired Midland in early 2022 to build 44 apartments at Ashbrook on the Howth Road in Clontarf, Dublin, for about €9.6 million, a price later raised to €10.8 million. The job was due to finish in March 2023. Problems with the water connection and other delays led to a dispute, and in February 2024 Baystreet ended the contract and called in Midland's bond. A Midland director said in court papers the work was then at or near practical completion.
Baystreet stopped taking part in the arbitration in September 2025, and its creditors put it into liquidation that month, with Tom Murray of Friel Stafford as liquidator. In February 2026, arbitrator David O'Leary found the termination unlawful and awarded Midland about €9.15 million with interest and damages. Earlier this month High Court President David Barniville gave judgment for about €9.86 million and allowed enforcement. The liquidator did not object and agreed to admit Midland as a creditor for €9.1 million. Midland had received no payment, the court heard.
The new claim against the directors and shareholders covers the award, interest and enforcement costs, according to High Court documents cited by the paper. Midland will ask for the case to go to the Commercial Court at a hearing set for this week. None of its claims against the individuals has been tested in court. McKeon did not respond to the paper, and Midland did not comment.
Midland said it had faced claims from its own subcontractors and suppliers after the termination. Meanwhile the 44 apartments sold for almost €23 million in total, the last in August 2025, according to the residential property price register.
Why it matters: A builder can win every round against a single-project developer company and still collect nothing once that company is in liquidation. Midland's suit tests whether the people behind such a company can be made to pay, and its own subcontractors and suppliers are waiting on the answer.