Haryana Orbital Rail Corridor tunnel caves in a sixth time, cracking homes in a Nuh village

Ground over the unfinished tunnel of the Haryana Orbital Rail Corridor sank for a sixth time on Nov. 22 and reached the first row of houses in Sahsola, in Nuh district's Taoru subdivision in India, leaving several homes with wide cracks, The Tribune reported.

Villagers told the newspaper a loud bang woke them early in the morning and they found deep pits in the fields next to their homes. One house, roughly 200 feet of village road and a stretch of land over 400 feet long went down. The sinking ground crossed the barricades the district administration had put up. Many families have locked their houses and left, some for rented rooms and some for makeshift huts, with their cattle. No one has been hurt.

The trouble began in early October in Patuka, part of the same panchayat, where residents asked the Nuh deputy commissioner in writing on Oct. 5 to stop the work. A bigger collapse on Oct. 10 damaged a government school and a house, dropped more than 500 meters of land and exposed a GAIL gas pipeline. Further collapses came on Oct. 30 and Nov. 4, when a government road gave way. Crews filled it with soil and it sank again on Nov. 18. Some 10 to 12 acres of farmland in Patuka are ruined, crops included. The pipeline was not hit this time.

A senior official of the Haryana Rail Corporation told The Tribune that the repeated collapses had upset the ground at the site. Work has stopped and the tunnel's starting point has been backfilled. Houses nearby were inspected and marked, and land acquisition has started. Digging will resume only after the land is acquired, on a new design shaped by the expert committee's report, the official said. That committee has not published findings. Villagers allege negligence and say no real safety measures were taken.

The corridor is a 126 km double-line railway from Palwal to Sonipat through Sohna, Manesar and Kharkhoda, with a 4.7 km twin tunnel through the Aravalli hills. Officials raised its estimated cost this year from Rs 5,618 crore to Rs 11,709 crore, according to The Tribune.

Why it matters: Six surface collapses in seven weeks over one tunnel drive, with homes now cracked, is the scenario settlement monitoring and pre-construction condition surveys are meant to prevent. Watch what the expert committee says went wrong and how the new design changes the dig.