Long Thanh airport faces a thin opening as 34 foreign airlines ask to delay their move
Five weeks before Vietnam's new Long Thanh International Airport near Ho Chi Minh City opens on December 24, 34 foreign airlines have asked to put off moving there until late 2027 or 2028, according to a civil aviation survey reported by VnExpress and The Straits Times.
Of the 34 carriers, 24 want to start at Long Thanh with the winter 2027 schedule, which begins in late October 2027, and 10 want summer 2028 or later, VnExpress reported from a report sent to the government. Airlines said they need six to 12 months to rework route networks, aircraft, crews, ground handling and ticketing. Cargo operators including UPS, FedEx, DHL and Cargolux want an express terminal, on-site customs and truck yards, and say their preparation could take about 12 months. Carriers also asked for reliable road links to the city and transit hotels of four stars or more.
Until late March 2027 the airport will open only the west wing and central part of the terminal and handle at most 366 flights a week, 322 of them domestic, Thanh Nien reported. Vietnam Airlines plans 72 weekly flights and Vietjet up to 294, all domestic, according to VnExpress.
The construction ministry warned that opening while parts of the site are still being built could hurt service, Thanh Nien reported. Trial operations started in late September, about three months before opening, a much shorter run than at Istanbul or Beijing Daxing, the ministry noted. About 86% of essential facilities were done as of late October, The Straits Times said, citing a government post.
The 336.63 trillion dong project (about S$16.9 billion) covers more than 5,000 hectares in Dong Nai province, roughly 50 km east of Ho Chi Minh City. It has faced worker and material shortages and a bidding scandal in which several executives were detained, The Straits Times reported. The first phase is built for 25 million passengers and 1.2 million tonnes of cargo a year.
Why it matters: Owners on fixed-date megaprojects often learn late that tenants need a year to move in. When a building is handed over before roads, hotels and cargo systems around it work, the commissioning period runs long and punch lists grow. Plan trial operations and tenant fit-out into the schedule.
Sources
- Hơn 30 hãng bay quốc tế muốn lùi thời gian khai thác ở Long ThànhVnExpress, Nov 18
- Vì sao 34 hãng hàng không quốc tế muốn lùi thời gian khai thác tại sân bay Long Thành?Thanh Nien, Nov 18
- Vietnam's new airport hits another snag as airlines seek to delay moveThe Straits Times, Nov 19