Vietnam starts $970 million Lach Huyen port expansion with four deep-water container berths

Vietnam broke ground on Nov. 23 on berths 9 through 12 at the Lach Huyen deep-water port near Hai Phong, a $970 million job backed by Singapore's PSA International that adds 1,800 meters of container quay and 4.5 million TEUs a year of capacity by 2035.

Prime Minister Le Minh Hung attended the ceremony, VietnamNet reported. The developer, Lach Huyen Port Investment JSC, is a venture of PSA International and Vietnamese developer Xuan Cau, according to ENR. The project covers about 146 hectares of land and water and puts the four-berth investment at nearly 24.85 trillion dong.

The plans call for four container berths along an 1,800-meter main quay, sized for ships carrying 12,000 to 18,000 TEUs, plus a 400-meter barge berth, container yards, repair shops and internal roads, VietnamNet reported. The berths will handle about 4.5 million TEUs a year, according to Hai Phong's finance department, as cited by ENR.

Work is phased. Berths 9 and 10 fall in the city's 2026 to 2030 schedule, and PSA said in July it expects to finish them in 2028. Berths 11 and 12 are planned for 2031 to 2035. PSA agreed on July 3 to invest in the port company and help build and run the terminal.

Lach Huyen already has six deep-water berths with more than 2.4 kilometers of quay and can take ships of nearly 214,000 deadweight tons, according to Hai Phong officials. The complex handled more than 1.37 million TEUs and 1,190 vessel calls in the first half of 2026, port authorities told ENR. A separate $575 million project for berths 7 and 8 brings planned investment across the two developments to about $1.54 billion.

Why it matters: Marine contractors and steel and equipment suppliers bidding in Southeast Asia have a decade of quay, yard and barge berth work ahead at Lach Huyen, starting with two berths due in 2028. For US importers it means more room at a port that already runs direct services to the US and Europe.